Tuesday, April 19, 2011
Fukushima issues 6-9 month containment plan
The operator of the damaged Fukushima Daiichi nuclear power plant has announced a schedule for getting the crisis under control in 6 to 9 months.
Tokyo Electric Power Company chairman Tsunehisa Katsumata explained the plan at a news conference on Sunday.
He said a two-stage process is scheduled. In the first stage over the next 3 months, TEPCO aims to cool the Number 1 and 3 reactors in a stable manner. It plans to cover fuel rods with water by injecting water into the containment vessels. The company also plans to purify contaminated water and return it to the reactors. It will set up heat exchangers to remove heat from the reactors.
TEPCO says it will contain the radioactivity leakage from the Number 2 reactor by patching the damaged section. Then it will take the same measures as at the Number 1 and 3 reactors.
In the second stage, TEPCO plans to lower the temperature of the fuel in the reactors to below 100 degrees Celsius to stabilize its condition.
Regarding the release of radioactive substances, it will set up water purification facilities to tackle highly contaminated water.
TEPCO also plans to put giant covers over the reactor buildings to prevent the release of radioactive substances into the air.
Regarding environmental monitoring, in the first stage, TEPCO will increase the number of monitoring points within the government-set evacuation areas. In the second stage, it will carry out decontamination to reduce radiation levels in the area.
University of Tokyo graduate school professor Koji Okamoto says officials must approach the work flexibly, be prepared for unexpected situations, and be sure to release plenty of information as they make progress.
NHK
hostgator coupon 2011
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment